Biomass Power’s Managing Director, Graham Parry, visited Full Circle Generation’s new 15MWe Energy from Waste plant in Belfast this week to check on the installation of the advanced conversion technology Gasifier, Combustion and Boilers. All Biomass Power major equipment deliveries are now in location with refractory work proceeding to plan. Biomass Power has completed the Process plant design and supplied the Gasification, Combustion, Boiler and Distributed Control System (DCS). It is expected that commissioning will begin in Quarter 2 2017, with take over planned before the end of the year. Graham Parry was thrilled to see the progress being made on site and very impressed by the 3 advanced conversion technology Gasifiers.